In the spring of 2000 DST was requested to undertake the following
task for SAS Congress Centre Bautahøj:
An extension of the existing waste water plant, built in 1996, according to the following
specifications:

 |
 |
The plant must comply with current relevant regulatory requirements with a waste
water capacity sufficient for 200 guests per day. |

 |
The plant must work without any emission of odour. |

 |
Owner's control and maintenance should be reduced to 2 x ½ hour per month. |

 |
Process monitoring of the waste water plant must be possible via the DST
network computer. |
|
 |
|
 |
|
In August 2000 after a 3-month design and construction period the renovated
plant was ready to receive and treat the waste water from the Congress Centre.
Quotation from the builing owner, May 2002:
"After the renovation, the waste water plant of
the SAS Congress Centre Bautahøj has been operating without any problems or disruptions
and has been in compliance with all regulatory requirements for discharge of cleaned waste
water."
|
|
|
 |
|
 |
 |
 |
 |
[Optimized for IE 1024x768]

 |
|
 |
|
|
|